Personnel, equipment and materials required for plastic runway construction

(i) Personnel

1. Construction Team Director: Project Manager 1

2. Site Leader: 1 Site Supervisor

3, full-time quality staff: 1

4. Part-time and part-time construction workers and security staff: 2 people

5, construction team personnel: 15-20 people

塑胶跑道施工

(b) Machines

1, high-speed mixer 1-2

2. Four-wheel carts 6-8

3, 1 sweeper or high power blower 1

4, paving machine 1

5, spraying machine 1

6, drawing machine 1

7, a group of other construction manual appliances

(c) Materials

1, the required materials:

Base oil PJT-190

Adhesive PJT-194

Plastic spray material PJT-195

Color paste, line paint, etc.

Black rubber particles 1-3mm

Red EPDM particle 0.5-1.5mm

2, material ratio:

(1) Primary treatment material: PJT-190;

(2) Substrate: Use a professional mixer to mix the slurry with the adhesive and black rubber particles in a ratio of 1:4;

(3) Compact layer: fill it with PJT-190+ filler;

(4) Surface spray coating: The surface material (PJT194: PJT195=2:1 is mixed) is mixed with EPDM powder and EPDM particles in a mixing ratio of 1:5:0.25.

3, material packaging, stacking and precautions:

(1) Bulk liquid materials are stacked on both sides of the runway in the parallel direction of the local prevailing wind direction of the construction season. The PJT-194 is packed in 200kg vats and is stacked vertically in a single layer. The pJT-190 and PJT-195 are used for piling. All are stacked in 30kg or 15kg keg, and the stacking height cannot be higher than 2 stories.

(2) The solvent used for dilution is generally packed in 170kg vats or packed in 15kg kegs, concentrated in a dedicated area and sent to special persons for management.

(3) Solid materials such as EPDM rubber particles and black rubber particles are piled on both sides of the runway in the parallel direction of the local prevailing wind direction at the time of the construction. The stacking force shall be firm and not loosened, and be covered with a waterproof stripe to avoid moisture.

(4) The construction tools are stacked on the side of the runway, and the power supply side adopts the special distribution box for construction and the “three-phase five-wire system” for safe connection.

(5) Machines are specially operated by qualified personnel. Special attention should be paid to personnel safety during operation.

(6) The ratio of materials is strictly controlled by the company's professionals and it is poundable at any time.

(7) The material should be stirred for more than 1 minute per barrel and thoroughly mixed.

Related Reading:

"Plastic Runway Construction Requirements and Maintenance"

Http://

Sevenze`s  sun lounge and Rocking Chair are designed well with unique styles. The material chosen is light, easy moving, which is the best combination of multiple courtyard space. It is wise to decorate by lounge and have a flexible usage of it no matter where it is, balcony, living room, garden or swim pool, getting the best experience in your life.

Sun Lounge

Sun Lounge

Sun Loungers,Garden Sun Loungers,Folding Sun Loungers,Outdoor Sun Loungers

SEVENZE INDUSTRAL CO.,LIMITED , http://www.sevenze.com